Madison Street's New Pete's Was a Sidewalk Deal as Much as a Grocery Store

October 22, 2026

The face is a mechanic's, molded in terra cotta and set high on a brick showroom wall. For decades, a row of these figures of mechanics and motorists looked down on Madison Street from the building at 644 Madison St. In a 2019 photo caption, Wednesday Journal called it "Motor Row Memories." Preservationists call figures like these grotesques. They're cousins of gargoyles, made whimsical here to fit a car dealership.

That wall came down in December 2020. The new Pete's Fresh Market stands on the site now, at 668 Madison St. It opened August 19, 2026, and Pete's lists it as open 7 a.m. to 9 p.m. daily. Most coverage treats it as a grocery opening that ran very late. The Village's agreement with Pete's paired millions in public money for the site with commitments from Pete's at street level, covering the pavement and those faces as well as the store.

What the Village put in, and what it asked for

The redevelopment agreement dates to 2018. According to Wednesday Journal's January 2023 report, the Village donated part of the site and gave Pete's $3 million to buy and demolish the Foley-Rice building. It added another $1.65 million for environmental remediation.

What came back went past a store. A January 20, 2021 memo filed with the Oak Park Plan Commission describes a streetscape along the whole Madison frontage, paid for by Pete's "as a compensating benefit" under the agreement.

Village contribution Pete's commitment at street level
A donated portion of the site Multi-colored brick paver sidewalk along Madison
$3 million to buy and demolish the Foley-Rice building Benches, bike racks and planter boxes
$1.65 million for environmental remediation A bus shelter and landscape islands
A large color-design crosswalk to the senior housing to the south
A display area for the Foley-Rice grotesques, lowered for pedestrians

The memo says plainly why the sidewalk mattered. Plan commissioners had worried about one long building filling two blocks. The redesign broke the south facade into three planes, enlarged the entrance tower and added accent brick, all "to make a more pedestrian friendly experience." At the December 2021 groundbreaking, Village President Vicki Scaman put the goal in the same terms, as Wednesday Journal reported: "a more walkable, shoppable, thriving neighborhood."

The building the deal replaced

The deal had a price beyond dollars, and the showroom's history shows what it was. Architects E.E. and Elmer Roberts designed the building as a showroom for Hill Motor Sales, a Packard dealer, and it was built in 1925. Its last use was as part of the Foley-Rice dealership, which had buildings on both sides of Madison and ended with a Foley-Rice Cadillac showroom here. Landmarks Illinois put it on its 2019 Most Endangered list. The group called it one of the best-preserved survivors of Madison Street's auto-sales district.

Preservation got a real hearing. Here's how the decision unfolded:

  1. 2019. The Historic Preservation Commission unanimously recommended landmark status. The Village Board declined it.
  2. November 2020. The Save the Hill Coalition brought in alternative plans that kept part of the building. Its members included Frank Lipo of the Historical Society of Oak Park and River Forest, Heidi Reuhle of the Unity Temple Restoration Foundation and architect Frank Heitzman.
  3. November 23, 2020. In a 5-to-2 vote, the board approved an amendment that dropped the showroom from the plan.
  4. December 2020. Crews took the building down.

Pete's explained the facade in practical terms. The loading dock had to go on the property's east edge, and a store had to fit across two city blocks. Developer Eugene Grzynkowicz estimated that keeping the facade would cost about $2.5 million, since the wall would have to be taken apart and rebuilt. "If I had it my way and I had an open checkbook, to make this happen, we could do it," Pete's executive officer Stephanie Dremonas said at the meeting, according to Wednesday Journal.

The grotesques were what survived on paper. The same article said Pete's would build them into the new store's design. By the December 2021 groundbreaking, the commitment covered "seven grotesques." The Plan Commission memo goes further and describes a "more prominent area for the display of the Foley Rice caricatures." At one commissioner's suggestion, the plan moved them lower so people walking by could see them at eye level. The opening-day coverage last August focused on the crowd and said nothing about them.

Why eight years, and who paid for the wait

The faces were promised at the start. The schedule took longer. The original agreement set an opening date of November 30, 2022. In January 2023, Tammie Grossman, the Village's development customer services director, blamed the delays on underground utilities. Crews had to remove and move lines belonging to AT&T, Nicor and ComEd.

"This is probably the most challenging development site that we have in the community."

Grossman told the board that in January 2023, as Wednesday Journal reported. Pete's had first contacted the utilities in September 2019. Removal was scheduled for March 2020, and then COVID-19 hit. The board moved the opening to June 30, 2024.

The agreement also built in a cost for delay. Pete's was supposed to have a Certificate of Occupancy by February 15, 2026, and missed it. By June 30, 2026, it had paid the Village $137,280 in lost-opportunity costs. That money is meant to make up for the sales tax, liquor tax and property tax growth the Village was missing. The meter ran at $45,760 a month until the certificate was issued. Those payments show what the Village expected the block to earn. At the 2021 groundbreaking, it projected about $587,000 a year in real estate taxes and $546,000 in sales taxes from a 46,000-square-foot store employing 140 to 180 people. Those were forecasts made five years before the doors opened.

The deal also fits a much longer effort. Oak Park put a tax increment financing district on Madison Street in 1995 to help revive the corridor, and the district expired at the end of 2019. The senior housing across the street, on the site of Foley-Rice's south-side building, came out of the same push. The color-design crosswalk in the plans links the two projects.

What the store is, two months in

Inside, it's a full Pete's, with a bakery, a popcorn station that makes specialty popcorn in the store, butcher counters and a fresh juice bar. It's the chain's second Oak Park store. The first is at 259 Lake St. On opening morning, Stephanie Townsend arrived around 7:40 for the 9 a.m. opening. "We waited 10 years, we can wait 10 more minutes," she told Wednesday Journal. Vanessa Dremonas, an executive officer and the daughter of founder James Dremonas, described to Wednesday Journal how the company approaches a new store. "Our goal is to always get it right about 90%, and then the other 10% is for the customers to tell us what they want."

Some of that 10% is already about the sidewalk. A September 1 letter to Wednesday Journal pointed out that the store has no pedestrian entrance on its north side. People walking in from the northeast have to go around to the front and enter alongside car traffic. The letter asked for a simple walkway. Parking under the 2021 plan puts employees in an underground garage and customers in a surface lot. The building was laid out for the Madison Street side, and the planned pavers, bus shelter and crosswalk were drawn for that side too.

The store also joined grocers already working this part of town. Carnival Grocery is at 824 S. Oak Park Ave., Sugar Beet Food Co-op at 812 Madison St., and a Jewel at 438 Madison St. Sugar Beet sits on the same Madison Street sidewalk that the Pete's frontage was redesigned to improve.

On the Madison Street side, the plans called for brick pavers, a bus shelter, benches and a display of seven terra-cotta faces at eye level. The Village paid $4.65 million toward the project, gave up part of the site and accepted a demolition the preservation community fought, and that frontage is what the deal promised in return.

If you're a Madison Street neighbor wondering how a project like this affects your block and what your home is worth, ZK Group follows these deals from the plan commission stage onward. We're glad to walk you through what's changing near you. Schedule a Consultation whenever it's useful.