Brick home entry with a dark wood door, stone arch, and divided-light window.

Oak Park Avenue Construction and the Hemingway District’s Return

October 8, 2026

In the week ending September 25, an AT&T crew was rebuilding a manhole at North Boulevard. Down the block, another crew got ready to pull up the pavement under the railroad bridge and the old plaza next to Citrine. Nine months into Renew the Avenue, the middle of Oak Park Avenue is still closed to through traffic. The Village's latest construction memo, dated September 24, 2026, says the project is on schedule and under budget. It is still expected to be substantially complete before Thanksgiving 2026.

The construction schedule is only half of what that memo describes. The other half covers the businesses. The money set aside to help them through construction has gone mostly unspent, and Village staff now propose putting what's left into one weekend: Thanksgiving weekend. The engineers finish in late November, and the Village is planning the district's reopening as a series of fall events timed to land right after that.

The street is coming back one block at a time

The project covers Oak Park Avenue from Ontario Street to Randolph Street. The work rebuilds water and sewer lines about a century old and redoes the streetscape above them. Parts of it have already reopened:

  1. June 12, 2026. Ontario to Lake and Randolph to Pleasant reopened to traffic. Street parking on those blocks stays closed until the landscaping is restored.
  2. Now. Pleasant to Lake is still closed to north- and southbound traffic. Lake Street, North Boulevard, South Boulevard, Pleasant Street and Randolph Street still cross the Avenue east to west.
  3. Late September. The Village's updates for the week ending September 25 had brick pavers going in between Pleasant Street and South Boulevard, sidewalks first and the roadway after that. The concrete roadway base on the block from North Boulevard to Lake Street was set to be finished by the end of that week. So was the last water main segment under the viaduct, along with the last four catch basins.
  4. Before Thanksgiving. This is the target for substantial completion. No official notice gives a calendar date for when through traffic returns.

Every business in the district has stayed open the whole time, reachable from the sidewalk. The Avenue Parking Garage at 720 North Blvd. offers 90 minutes of free parking from February through December 2026. The Village Board started the extended free time a month earlier than first planned.

A plainer street than the 2023 drawings

If you remember the early renderings, the finished Avenue will look simpler. The project went out for bid twice. In the earlier round, the only bid came in nearly $5 million over the $18 million budget. The Village then cut more than $300,000 by dropping custom fencing, special lighting and granite sidewalk pavers. The following August, the board switched the new sidewalks from bluestone to concrete pavers, which took nearly $1 million off the total. On November 11, 2025, the board awarded the $18.5 million contract to A Lamp Concrete Contractors.

Village President Vicki Scaman described the cuts at the time as "items that down the road that we can always add." Here is what the current construction updates confirm for the finished street:

  • New light-pole and traffic-signal foundations, already in place between Pleasant Street and South Boulevard
  • EV-charging infrastructure along South Boulevard
  • A curb bump-out at the southeast corner of Oak Park Avenue and South Boulevard
  • Structural soil and irrigation for street trees on the north block
  • Brick pavers on the roadway and concrete pavers on the sidewalks

The viaduct will change the most. The love locks that covered its wall were removed after a Valentine's Day "Tokens of Love" event on February 14. Any locks left unclaimed were recycled and won't be reused. A custom panel system will replace them, with illuminated arch cut-outs framing a mural made for Oak Park. The project site has posted the final viaduct mural renderings. Other ideas from the 2023 design coverage, such as green walls and a lighted monument, don't appear in this fall's construction updates.

How the businesses got through the year

In February, Wednesday Journal reported on the strain at Café Cubano, Grape Leaves, George's Family Restaurant and Il Vicolo. Il Vicolo co-owner Frank Russo said the restaurant planned specials to bring in diners. George's owner George Konstantos noted that grants for exterior improvements don't cover rent, operating costs or payroll.

Some help came from neighboring businesses. Maya Del Sol has offered valet parking since it opened in 2007. In June it added spots at St. Edmund's Church and opened the $5 service to customers of any Oak Park Avenue business, with pickup in the alley behind the restaurant. Managing partner Chris Ramirez explained why:

"The construction is temporary, but a season can really affect the business."

The Village's main tool was the Renew the Avenue Business Grant Program. It offered up to $5,000 per storefront in each of three categories: facade improvements, interior improvements and social media marketing. For the first time in Village history, businesses that don't generate sales tax could apply. The September memo lists who received grants. The amounts below combine each recipient's awards:

Recipient Total grant awarded
Trade Oak Park $40,000.00
Yoga Loft $8,825.00
Lively Athletics $6,833.50
Cucina Paradiso $5,000.00
The Wolf Oak Park $5,000.00
Color Me Mine $5,000.00
Village & Vessel $5,000.00
814 North Blvd $5,000.00
Dental Care of Oak Park $4,500.00
Dandelion Bookshop $2,650.00
CandyCopia $1,000.00
Total $88,808.50

That $88,808.50 supported $472,271.31 in improvements, so each grant dollar matched more than five dollars of work. The district's storefronts will look noticeably different once the fencing comes down. The budget was $305,000, though. Even after staff add the roughly $60,000 more they expect to award by year-end, the memo projects $156,191.50 left over. Applications stay open through December 31, 2026.

The memo also describes smaller help that cost businesses nothing. Contractors have washed storefront windows every three to four weeks since July, and the last cleaning in November will include awnings. Staff hold one-on-one meetings from a Renew the Avenue office at 104 N. Oak Park Ave. A weekly email for the district, the "Thursday Three," is open to anyone who signs up on the project website.

Where the leftover money is headed

The memo proposes putting that balance into the holidays. Staff are putting together a coupon book covering all twelve of Oak Park's business districts. Some Hemingway District businesses may want to take part but can't afford to absorb a discount. For them, the Village would reimburse up to 15 percent of the final bill, based on submitted receipts. The coupons would be valid November 27 through 30, the weekend of Small Business Saturday. It's still a staff recommendation to the Village Board, not an approved program.

That weekend comes at the end of a fall calendar the Hemingway District has already published:

  • Through Saturday, October 31: Bike to the Biz. Collect receipts from four district businesses with at least $10 spent at each, and drop them off at the UPS Store. Each month's winner gets a $250 voucher good at any of Oak Park's three bike shops.
  • Saturday, October 17: Fall Family Fun, 10 a.m. to 1 p.m. Costumed kids and caregivers line up near the Main Library entrance at 9:45 a.m. Village President Scaman leads the parade through Scoville Park at 10. An Early Childhood Resource Fair for families with children up to age five runs inside the library until noon, and participating businesses along the Avenue hand out treats.
  • Saturday, November 14: On the Road Again Celebration, 10 a.m. to 8 p.m. The district calls this its grand reopening and hasn't released details yet. The Village memo includes $7,500 for The Mix Road Crew to appear and promote the event regionally.
  • Saturday, November 28: Shop Small + Tree Lighting Celebration, 11 a.m. to 5 p.m. Deals, activities and a tree lighting.

The order of these dates matters. The reopening party comes about two weeks before the Thanksgiving target for substantial completion. The tree lighting falls in the middle of the proposed coupon weekend. By then the Village will have spent eleven months marketing the district as open behind construction fencing. The November dates are the first chance to promote it with the fencing gone.

Wednesday Journal's August roundup of the Hemingway District listed Dandelion Bookshop and the Main Library for books, and Maya del Sol, Rustico, Il Vicolo and Scratch on Lake for dinner. For coffee and pastry it named Spilt Milk, Mulata, The Wolf, Fairgrounds Cafe and Courageous Bakery and Cafe. It also mentioned Geppeto's Toy Box, Oak Park Records, Olive and Well, Lively Athletics and CandyCopia, all near Unity Temple and the Hemingway birthplace. Wednesday Journal reported in January that some storefronts in the district had sat empty for some time. We haven't found any new tenants announced for them yet. The rebuilt street, the refreshed storefronts and the November events are the Village's case for filling them.

Our team follows the Hemingway District from close by. A finished streetscape and a fuller calendar are the kinds of block-level details that come up when we talk with clients about pricing a home in central Oak Park. To talk through what the rebuilt Avenue means for your street, ZK Group is happy to help. Schedule a Consultation.

Partner with ZK Group

From the first consultation to closing, we are with you every step of the way. With deep local market knowledge, transparent communication, and an unwavering commitment to excellence.